Morro Bay Water Reclamation Facility Project:  Issues, Concerns, and Solutions



Recommended Solution


Morro Bay needs to resolve its WWTP problem quickly in a cost-effective, environmentally responsible way.  13 years of failures demonstrate that the approach the City has been taking doesn’t work, and that the solution that may have been considered ideal is simply not practical,  reasonable, or even do-able.  


We need a common-sense solution that:


Yet, the current general design for the plant is subject to the exact same risks of failure as the existing plant.  In terms of risk, the current design is actually worse than leaving the plant right where it is.

It also seems reasonable to assume that the CCC does not want to drive the City and/or its residents into bankruptcy.


The recommended solution includes two major components, the site, and the project approach.


Site


The solution recommended by the owners of this site and supported by many residents is to build the new plant on the property formerly occupied by Hanson’s Concrete.  By building on that site, the City could save taxpayers tens of millions of dollars and, with the right technology, get a plant up and running very quickly. With the right technology and protective measures, the plant could be made safe from natural hazards for the duration of its projected useful life.   


ADVANTAGES of this site include:



CHALLENGES of this site include the following issues and concerns identified by the Coastal Commission.  Most were identified in a November 12, 2012 letter written by Coastal Commission staff member Madeline Cavalieri:


Addressing these challenges is not only possible, but highly-feasible and would not generate any excessive costs.  Location of the WRF on the Hansons’ site is no more risky than the current plan to locate an inland WRF’s a giant lift station on the WWTP site.  That is due to the fac that, if the lift station fails, sewage cannot be moved to an inland plant, and thus the whole system fails.


 In addition, other important facilities - Morro Bay High School and the City’s desalination plant, are located in the same area and are not being moved.  



Project Approach


The approach the City has been taking so far has benefited only the highly-paid consultants and engineering firms that have no incentive to ensure that time and costs are minimized.   Inefficiency, poor planning, mistakes, and rework are essentially “profit centers” for some. The longer the project takes, and the more work required, the more money the consultants and engineering companies make at taxpayer expense.

Morro Bay can learn from the town of Strasburg, Virginia, where “thinking outside the box” brought that community a major upgrade and expansion of their WWTP.  It was completed under budget and finished in about three years.  

Strasburg ran into financial problems with their WWTP project.  In July, 2012, their consultant told them that the plant, as designed, would cost about  $20 million. Then, they put the project out to bid, and 4 months later, in November, 2012, the bids came in.  The lowest bid was over $31 million.  They couldn't afford that.

So, they decided to back away a bit from their design, and see if someone could come up with innovative solutions that would give them a quality plant that would meet their capacity needs and the requirements of regulatory agencies, AND would not cost more than what they could afford to spend.  They issued a Request for Information (RFI) and asked for just that.  Responses were due in February, 2013.

Strasburg ended up getting a letter of interest from a well-established company that offered to build their plant for them at a guaranteed cost way below the previous "low bid" of $31 million.  Morro Bay residents got an update from Strasburg on October 3, 2016.  They were just finishing up their project.  

In just over three years, Strasburg completed a successful project.  Their costs were within budget, and the product is exactly what was needed.  In contrast, Morro Bay has been trying to achieve the same result for  for 13 years and has completely failed.

The current estimate of Strasburg’s savings, achieved because their City government  issued that RFI, is $15 million.  The residents of Strasburg got just what they needed for a price they could afford, and are very happy with the results of the project.

Had they not left their options open, and had they not been wise enough to use an RFI to tap the pool of expertise that is comprised of numerous engineering companies worldwide, many of which they had probably never heard of, they would not have gotten a cost-effective solution to their problem and would have had major financial problems as a result.

There are many kinds of sewage treatment plants, and new technologies are being developed.  Some designs are more suitable than others in dealing with natural hazards.  By following the Strasburg approach, Morro Bay can get an affordable plant with safeguards that will ensure safe, reliable operation for decades.

This approach will probably not be popular with consultants and engineering companies that view Morro Bay as a “cash cow” - an opportunity to make a lot of money for themselves.  It is, however, what Morro Bay residents need.


One important aspect of this approach is the fact that it can be used to address the challenges of the site.  It will give the City the opportunity to tap into the expertise of engineering companies all over the country, making it possible to find the best way to build a safe, reliable facility on the Hanson’s site and address all of the Coastal Commission’s concerns.  Best of all it costs nothing more than the negligible costs of preparing and issuing the RFI.